How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / manish katiyari
finished volume=12mm = 0.012m =1.2m3
prop 1:6=1+6=7
cement req= 1.2/7
=0.17143
1cement bag=34.5 litres
=0.0345m3
cement bag req= 0.17143/0.0345
= 4.97 bags
approx = 5 bags
Is This Answer Correct ? | 16 Yes | 20 No |
Post New Answer View All Answers
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.
rcc floor to floor 4m. in column reinforcement where we provide lap in exact location.
How to find out slope footing concrete
How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete
What is thumb rule in quantity and cost estimation of a residential building?
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
What are some facts about concrete?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
sir please send me campus placement questions in civil engineering
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
RR masonry rate analysis
What are your goals?
What is the difference between one-way slab and two-way slab?