In any process Industry, Instrument to be mounted properly
to get the Correct Reading. Hook-up drgs provides detialed
information about Instrument Installation with respect to
the Process Fluid.
Also Hookup drawing is use to specify the Scope of Piping
Department and Instrumentation Department.
Also Hookups are required for Operation and Maintation.

It Provide the the details of Bill Of Materials..

Is This Answer Correct ?    12 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is loop1 and loop2 in MTS LT?

4200


hello sir/madam, I,Subramanian need 5yrs placement papers of officer trainee of Instrumentation technology.pls send to this mail id mani_nxtgen@yahoo.co.in please do the needful. with regards, subramanian.v

1775


what is instrument philosophy

1768


If we increase only P what will be controller action ?

1645


What is difference between “Fault Tolerant” & “Fault avoidance” PLC? Application where these system s are used?

3456






why we are using digital signals for I/O & how to measure this signals is getting or not ?

1555


Define cryogenic?

734


Regarding , there is an air cooler which control the fans(50% of AV FANS) by temperature in outlet , and the louver of Air cooler is controlled by HIC from control system , So if on Air cooler we will consider 2 individual I/P converter or positioner?

1375


what is orfics working in main steam line. is it increase pressure, velocity of steam flow and dicrease steam flow rate. or any other

1698


give some question relative instrument fitter?

5812


what is the working principal of pribe

1824


Can Any body tell me how to check Modbus Settings in ER300N L&T trivector meter?

2057


In Safe Guarding test what means by "Failed to Danger" ?

1667


Linear amplifier.

1556


why we are using magnet for calibration of gas detector?

1824