1)What is Suggested type of cement for concreting at water,
for mass concreting and where the chaces of gettin attucked
by salt?
2)How many types of camber?
3)why we always preffer short column in case of residential
building?
4) Is there any advantages between the use of One way slab
& two way slab?
5)What shoul be the % of steel for R. C. C. perpose based
on volume & area ?
Answer Posted / sujeeth
1) Generally for concreting under water we use concrete of
grade M20 or above and use plasticizers which reduce the
setting time and most imptly concrete shud not be released
from a height above 1 to 1.5 meter.
4) In one way slab, reinforcement is designed in such a way
that load is taken only by main steel and the purpose of
distributed steel is only to keep mail steel in position.
Whereas in two way slab, steel design is made suchthat load
is distributed over sntire reinforcement.
5) %age of steel by area in RCC beams and columns must
be < 4% and exact % depends on design of the structure.
P.S : Post questions 1 by 1 so that ppl can mark write and
wrong ans differently
Is This Answer Correct ? | 21 Yes | 6 No |
Post New Answer View All Answers
What is the withdrawal force of steel nails?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
How do we determine the specific gravity of a cement?
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
Why is concrete cube test carried out?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
How much is the cover for slab?
What are the methods of measurement? Describe it shortly
What are the responsibilities of a site manager?
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
Rate analysis of Vitrified tile in cement mortor 1:3
Define What is the origin of name Railway Sleepers?
why is M30 grade Concrete use for Foothing & Column M50
What are the different softwares used for cad?