In footing (mat) if two different dia of rods are to be used
which rod should be placed at top and bottom ( eg. 10mm &
16mm dia rods)
Answers were Sorted based on User's Feedback
Answer / ramesh k
Always bigger dia should be laid at bottom and it should be
provided on shorter directions.but for cantilever beams and
sunshade bigger dia should be laid at top,the reason is the
mat shold be laid at top.
Is This Answer Correct ? | 11 Yes | 1 No |
Answer / ramesh konduru
Always bigger dia should be laid at bottom and it should be
provided on shorter directions and also depends upon load
coming on the columns.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / maaz ahmad
Mainly the selection of dia bar will depend upon the cross
section . the bigger dia will be used along the shorter span.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / md.nazimul islam bhuiyan
In bottom net bigger dia rod at bottom & In upper net
bigger dia rod at top
Is This Answer Correct ? | 2 Yes | 1 No |
Answer / babu lal nayak
16mm dia bar laid at bottom parallel to short span & 10mm dia bar at top parallel to long span.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / gurmeet
it will be smaller dia bars which will be placed at bottom
because the bottom part will be under compression and the
upper part will be under tension. This is because the base
preassure is acting from downward direction.
Is This Answer Correct ? | 6 Yes | 25 No |
how to calculate the quantaty of steel in footing please show me detail procedure with the help of drawing
where the corner reinforcement be placed in the rigid road pavement? can it be placed below the bottom main bar of double netting pavement?
what is the difference between volume and weight batching and which is better?
Sir how to find cutting length for footing steel bars in the shape of "u"
What is the stripping time of shuttering for PPC concrete
What is the Alternative material of cement, We use for Floor tilling and Wall tailing purpose?
i know that, the for calculating material required for concrete volume of concrete is taken 50-54 % more for wet volume. i have querry is that cement and sand volume taken more for making wet volume but in the case of aggregate why it is taken more there is no change in aggregate whether it is dry or wet.???? can you give me answer for this???
what is scour depth $ what's the process to determine it?
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
in plate load test what is the thickness of plate 20mm 5mm 50mm none
per 1 cumt concrete how much manhours is required including shuttring,steel etc.,for slab & foundations
How much overlapping required for welding the reinforcement bars in Columns & beams