what is the process of repair the structure in whitch reinforcement is open..

Answer / jayshankar dwivedi

Situation is called honeycombing. Prepare a mix with GP2
and apply on portion

Is This Answer Correct ?    11 Yes 0 No

what is the process of repair the structure in whitch reinforcement is open..

Answer / balamurugan

simply filled with cement mortor in 1:2 ratio in honeicombes without caveges

Is This Answer Correct ?    2 Yes 0 No

what is the process of repair the structure in whitch reinforcement is open..

Answer / nandkishor kabra

repair can be done by guniting(applying cement and sand
mixture with the aid of compressed air )

Is This Answer Correct ?    2 Yes 0 No

what is the process of repair the structure in whitch reinforcement is open..

Answer / sumit

That situation shoe is honeycombing
So he is repaired with a mix of Nitobond & cement & water

If honeycombing is visible in big area then Jacketing
Method Applied (If possible)

Is This Answer Correct ?    2 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

what is difference between bending and twisting

4 Answers   Sam India,


The Instrument used to determine colour of water is called A] Turbidimeter B] osmoscope C] Barometer

1 Answers  


What is bylayer?

0 Answers  


plastering ratio 1:3

3 Answers  


how much water you will add to the mix, for making 1 m3 of concrete to achieve strength of mix 20N/mm2 at 28 days.

11 Answers  






WHICH IS BETTER,BURNT BRICKS OR SOLID BLOCK IN CEMENT MORTAR

2 Answers  


Unit weight of sand

3 Answers   SPML,


I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com

0 Answers  


I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.

0 Answers   TVO,


12 mm dia not available at site for raft, 10 mm are available at site how to calculate?

8 Answers  


All aptitude question of Bechtel

0 Answers   Bechtel,


brick work with 1:6 cement mortar how many bricks and cement and sand require for 1cum

3 Answers   Arma Group,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)