Laboratory experiments conducted in Mumbai on a particular
mix showed a
strength of 33 MP a for a fully matured concrete. Find
whether formworm
can be removed for an identical concrete placed at Jammu at
the age of 15
days when the average temperature is 60C. The stripping
stress in concrete
Answers were Sorted based on User's Feedback
Answer / buntychandwani
First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.
Now,
Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH
Plowman's Constant given as A = 21 and B = 61
Se/S 15 = A + B Log10 [ M /1000]
Percentage of strength = 21 + 61 log(6120/1000)
= 68.99
The strength of Concrete at 15 days = 33 x (68.99/100)
= 22.76 Mpa
Since the strength of concrete is less than the stress
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / buntychandwani
First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.
Now,
Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH
Plowman's Constant given as A = 21 and B = 61
Se/S 15 = A + B Log10 [ M /1000]
Percentage of strength = 21 + 61 log(6120/1000)
= 68.99
The strength of Concrete at 15 days = 33 x (68.99/100)
= 22.76 Mpa
Since the strength of concrete is less than the stress to
which it is likely to be subjectd while stripping the
formwork, the concrete may fail. Therefore, the formwork
cannot be removed at 15 days time.
Is This Answer Correct ? | 1 Yes | 1 No |
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
What is the per square fee cost of external development of a multistorey group housing project
rate analysis for shuttering 1:6
what are the values of compressieve strenght?
what are the tests conducted on cement,aggregate and concrete?briefly explain that tests procedure and limits adopted for safety side.
how to remove the quantity of metal 1 and metal 2 in concrete
How to determine dia of steel for use in column,slab etc. i mean how to calculate the diameter of steel which is to be used in structures.
What is difference between combin footing & rapt footing
What is meant by engineering drawing?
how to calcalate for roof beams & slab reinforcement design specified?
how to convert sand from Cum to Brass
14. List 3 of your strongest points as a worker?