WHAT IS THE DIFFERENCE BETWEEN SHOP DRAWINGS/ DESIGN
DRAWINGS AND AS BUILT DRAWINGS??
Answers were Sorted based on User's Feedback
Answer / prashant
When we are qouting for a project its on the basis of
TENDER DWG
After that we start prepearing the SHOP DWG ie for use at
site and as per this dwg work has to be executed at site
Finally we have to prepare the AS BUILT DWG ie the exact
dwgs as to how the work was carried out at site bcoz at
site due to the site conditions the site engg mite have
laid the wire or the conduits thru a diif path as shown in
the shop dwg. All such deviations are to be shown in the AS
BUILT DWG
| Is This Answer Correct ? | 53 Yes | 8 No |
Answer / hamid
the shop drawing is engineering DWG and may can be
change during the construction or installation of
equipment after test .
the Hasbult drawing is the final drawing after
commissionning of installation and the last change if it
has a changement
| Is This Answer Correct ? | 16 Yes | 8 No |
How can I model an open-delta ground transformer for a network supplied by 4 unit GTG and power transformer in ETAP?
what is the difference SCR & TRIAC?
5- What is the task (function) of the excitation and isolation transformers in power plant? 6- What is the task (function) of LCI (A), LCI (B) and LCI (COS) in power plant? : LCI (A) and LCI(B) are load commutating inverter for generator turbine starting. , LCI (COS) is load commutating inverter change over switch
in HT service 3ph 4 wire service Y-phase voltage shows zero . whether it is meter fault? or what be the reason ? if y-ph voltage zero ,can current is recorded? reasons for failure?
what is fundamental difference between voltage and current
define briefly the function of an ac electric generator (alternator)?
what will happen if we will not use commutater means if we will give dc to the windings in dc motor
how to find ratio of CT & PT in 66/11kv 12 mva supply system ? explain with calculation.
What is the output of below program? #include <stdio.h> int main() { int p,q; for(p=1,q=1;p<7;p++) { printf("%d%d__",p,q); } return 0; } Answers- 1. 17__27__37__47__57__67__ 2. 11__21__31__41__51__61__ 3. __11__21__31__41__51__61__ 4. Compilation error
flush point of transformer?
how to make an earthing certificate
can u please mail me the syllabus for GET exam for damodar valley corporation?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)