Answer / varun.j
while going for the concrete mixing we have to take
precausions for the oldness of cement which is the ultimate
bounding material shouldnot be older than max six months
about aggregate it should be free from every suspended
forain particals like clay dust and mud and in sand it
should be more that .4mm water which added should be bet 6
to 8 ph value..............
Is This Answer Correct ? | 12 Yes | 2 No |
Answer / guest
Aggrigate size, water cement ratio, water quality, sand
(coarse),grade of cement.etc
Is This Answer Correct ? | 2 Yes | 2 No |
Answer / vijendra singh
Aggrigate size, water cement ratio, water quality, sand
(coarse),grade of cement.etc
Is This Answer Correct ? | 0 Yes | 4 No |
What is meaning of FREE STANDING STAIRCASE ?
What is the cutting length formula of tringle ring?
Terms Name the bars which is used in beam and colume ? Like starter bar etc.
what is meaning of GSB? properties, ingradiant of GSB?
Time required for curing of wall tiles before fixing
What is the spacing of chairs in reinforcement steel.If it is written in IS 456:2000 then tell me the page number.
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
What is ideal location for cube casting, RMC vehical at Ground Floor and Slab casting at 40th Floor
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
Difference between lime, distemper and plastic emulsion?
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
plz anyone can tell me how to find the volume of dome whose radius is 3.25mt , height is 1.50mt and thickness is 0.15mt.