Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process?
A. Integrated Change Control
B. Scope Change Control
C. Schedule change control
D. Cost change control


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response? A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact. D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.

0 Answers  


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating

0 Answers  


what is software project planning?

0 Answers  


You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210

0 Answers  


All of the following are benefits of meeting quality requirements except: A. An increase in stakeholder satisfaction B. Less rework C. Low turnover D. Higher productivity

0 Answers  






You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.

0 Answers  


Describe resource planning during the estimation of software project.

0 Answers  


What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action

0 Answers  


If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

0 Answers  


You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following? A. Procurement planning B. Sensitivity analysis C. Transference of risk D. Make or buy analysis

0 Answers  


what do you do after a milestone is completed?

1 Answers  


How do you handle change request?

0 Answers  


Categories