Your hardware vendor left you voicemail saying that a potential snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and asked that you return the call. Which of the following is true?
A. This is a secondary risk, which is an output of Risk Response Planning.
B. This is a contingency plan, which is an output of Risk Response Planning.
C. This is a risk, which is an output of Risk Identification.
D. This is a trigger, which is an output of Risk Identification.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

PERT is: A. The longest path B. A weighted average technique C. A simulation technique D. Widely used in practice to determine schedule durations

0 Answers  


You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months

0 Answers  


All of the following describe the activity list except: A. It's an extension of the WBS. B. It includes all activities of the project. C. It describes the WBS updates. D. It includes a description of project activities.

0 Answers  


Why do you want to switch over from IT to management?

0 Answers   EX,


The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

0 Answers  






You work for a company that writes hilling software programs for the communication industry. You've just been assigned a new project. The customer is located in a distant country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You might do which of the following given these circumstances? A. Use a design of experiments technique to develop a contingency plan. B. Develop a cause-and-effect diagram that identifies the contract type you should use for a project like this. C. Use sensitivity analysis to assist you in developing the appropriate risk response for this situation. D. Develop a contingency plan for installation.

0 Answers  


A negative result from an SV calculation means which of the following? A. PV is higher than EV. B. PV equals one. C. EV is higher than PV. D. EV is higher than AC.

0 Answers  


You are a project manager for Zippy Tees. Your selection committee has just chosen a project you recommended for implementation. Your project is to manufacture a line of miniature stuffed bears that will be attached to your company's trendy T-shirts. The bears will be wearing the same T-shirt design as the shirt they're attached to. Your project sponsor thinks you've really impressed the big boss and wants you to skip to the manufacturing process right away. What is your response? A. To agree with the project sponsor because they are your boss, and they have a lot of authority and power in the company. B. To require that a preliminary budget be established and a resource list be put together to alert other managers of the requirements of this project. This should be published and signed by the other managers who are impacted by this project. C. To require a project charter be published and signed off on by all stakeholders before proceeding. D. To require a project charter be written to include the resource needed, budget, and project manager's authority. The project manager is the only one who needs to see this document as other documents will be distributed later that contain the same detail as the charter.

1 Answers  


You are constructing a probability/impact risk rating matrix for your project. Which of the following is true? A. The PI matrix multiplies the risk's probability by the cost of the impact to determine an expected value of the risk event. B. The PI matrix multiplies the risk's probability scales, which fall between 0.0 and 1.0, and the risk’s impact scales to determine a risk score. C. The PI matrix multiplies the risk's probability by the expected value of the risk event to determine the risk impact and assign a risk score based on a predetermined threshold. D. The PI matrix multiplies the risk's probability scales and the risk's impact scales, which fall between 0.0 and 1.0, to determine a risk

0 Answers  


What are the Scope Planning process tools and techniques? A. Benefit/cost analysis, work breakdown structure templates, expert judgment, and supporting detail B. Product analysis, benefit/cost analysis, alternatives identification, and expert judgment C. Product analysis, work breakdown structure templates, supporting detail, and expert judgment D. Benefit/cost analysis, alternatives identification, supporting detail, and expert judgment

0 Answers  


You are a project manager who has recently held a project team kickoff meeting where all the team members were formally introduced to each other. Some of the team members know each other from other projects and have been working with you for the past 3 weeks during the Planning processes. Which of the following is true? A. Team building begins once all the members of the team are identified and introduced to each other. This team is in the storming stage of Team Development. B. Team building begins at the Planning process. This team is in the storming stage of Team Development. C. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of Team Development. D. Team building begins at the Planning process. This team is in the forming stage of Team Development.

0 Answers  


All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction

0 Answers  


Categories