Which of the following is true regarding the Resource Planning process?
A. Resource Planning involves the human resource aspect of planning only, and its output is staffing requirements.
B. Resource Planning involves the human resource aspect of planning only, and its output is staffing requirements.
C. Resource Planning encompasses all the physical resources needed for the project, and its output is staffing requirements.
D. Resource Planning encompasses all the physical resources needed for the project, and its output is resource requirements.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following to identify the variables that will have the greatest effect on project outcomes? A. Design of experiments B. Bench marking C. Benefit/cost analysis D. Flow charting

0 Answers  


You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?

0 Answers  


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

0 Answers  


This process applies evaluation criteria to the bids and proposals received from potential vendors: A. Solicitation B. Contract Administration C. Source Selection D. Quality Assurance

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  






The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures

0 Answers  


As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity

0 Answers  


What is your management Style

8 Answers   ABC, Hospitality, Thomson,


You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true? A. The new machine, the concentrated formula, and the smaller package are each project constraints. B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document. C. The new machine, the concentrated formula, and the smaller package are each project assumptions. D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.

0 Answers  


Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.

0 Answers  


What do you mean by business object,condition object and costomising object?

1 Answers   DELL, Satyam,


Describe capability maturity model (cmm).

0 Answers  


Categories