How to calcuate the quantity of cement,sand for plastering 1:4 12mm thick?
Answer / nikita khanadre
Volume of plaster=1m*1m*0.012m=0.012cum
Dry volume=0.012*1.33=0.01596cum
Cement =1/(1+4) *0.01596=0.003192cum/0.035=0.0912 bag
Sand=4/(1+4)*0.01596=0.012768cum
Is This Answer Correct ? | 2 Yes | 0 No |
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
How to calculate the steel for 392c.meter*450c.meter rcc slab
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
what is the difference between built-up area & carpet area? how to calculate this areas?as there are any formula to calculate these areas?
where the corner reinforcement be placed in the rigid road pavement? can it be placed below the bottom main bar of double netting pavement?
What are the benefits of rcc pipes over steel designed pipes?
How do you derive the quantity of cement & sand in brick work construction in 1Meter cube, using CM 1:6 and bricks of size 19*9*9 cm
What are your future hopes for this job?
what is anchorage? Why anchoring of reinforcing bars necessary and what are the shapes ?
what are the major benefit in auto level?
Why beam breadth smaller than depth
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
0 Answers L&T, Rail Vikas Nigam Limited RVNL, RRB,