We have 11kV/110V three phase indoor potential transformer in 66/11kV Sub-station, where the failure of PT is frequently happening and the rating of the PT is 0.2 class accuracy, with primary star and seconday (two cores) star connected.
Some experts has suggested to not to connect the PT Primary neutral to the ground because when transformer neutal NCT connection is loose; the faulty current will flow through the PT primary neutral, resulting into failure of PT.
My question is: Is it necessary to remove the primary neutral connection of the PT from ground? if not, what would be the reason for failure of PT.
Please guide me.

Answers were Sorted based on User's Feedback



We have 11kV/110V three phase indoor potential transformer in 66/11kV Sub-station, where the failure..

Answer / k.prakashchandra

Intimate whether PT fails whenever there is an earth fault and which winding fails

Is This Answer Correct ?    0 Yes 0 No

We have 11kV/110V three phase indoor potential transformer in 66/11kV Sub-station, where the failure..

Answer / karthikeyan

hai mr.gokul,what kind of failure in pt,please tell me.i will clear this problem..,

regards,
karthikeyan
+919095206722 (whats app)

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

how do you calculate IKW(consumption per TR) in HVAC?

27 Answers   Aircon, CBRE, Cipla, Clivet, Cushman Wakefield, JLL, Sodexo, Voltas, Wipro,


why transformer rating is expressed in kva.

4 Answers   Electrosteel, L&T,


can you tell me/show me, how to manually synchronize 2 DG. preferred with video.

2 Answers   Cummins,


What is a commutator?

0 Answers  


What is the min and max ohmic value for earthing?

15 Answers   NewTek, Wipro,






Define delay time.

0 Answers  


why CT output is always raetd 5.regardsof primery curre.

3 Answers   ABB, BARC,


working function importance of mdc meter

0 Answers  


i want to know how to calculate the battery capacity based on the UPS . ex i want to run have one kva UPS Which should run 10 hours ? in that case how many batteries to be installed and what will be the AH Value .

2 Answers  


what is lightning arester?generaly which type of used in industeries? why its used?

7 Answers   Essar,


how to stop oil leakage in power transformer.

1 Answers   APGenco,


Why we are using air gap magnetic condutors

2 Answers   Ford, IOCL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)