How to calculate Brick for 9"wall for100sqft

Answers were Sorted based on User's Feedback



How to calculate Brick for 9"wall for100sqft..

Answer / abc

100 Sqft = 9.293 Sqm------A
9" = 0.230 M--------B
Volume of B/w = A x B => 9.293x0.230 =>2.137 Cum
Nos. Bricks @ 494 Per Cum. => 494x2.134 = 1056 Nos.

Is This Answer Correct ?    2 Yes 2 No

How to calculate Brick for 9"wall for100sqft..

Answer / er.darshan

but we will not consider 9" brick masonry is sq.ft.
the measurement or payment unit is cu ft

if size of brick is Actual = 19*9*9 cm or nominal size = 20*10*10 ( with mortar joints )
so,
1m3 brick work 500 brick are required
volume of bricks = 500 ( size of brick , actual ya nominal )
hear i consider = actual size of brick = 19*9*9 cm

= 500 x ( 0.19 x 0.09 x 0.09 )
= 0.77 m3
= volume of mortar = 1 - 0.77
= 0.23 m3 ... wet volume
= 0.33 m3 .... dry volume.

Is This Answer Correct ?    1 Yes 3 No

How to calculate Brick for 9"wall for100sqft..

Answer / civil engineer

100 multiply by 9 inch

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

what is the grade of concrete?

3 Answers  


column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial

0 Answers   Era Infra Engineering, Tricom,


what is the development length?

2 Answers  


What is missing report and how to prepare

0 Answers  


( mean sea level )for which activity we will use this statement?

3 Answers  






how to determine H- zone in a column? where it will occur?

0 Answers  


state the functional requirement of a retaining wall

5 Answers  


what is the weight of 1 meter iron road if its diameter is 20milimeter. 2.when we find the weight of 1meter iron road we help the following formula dxd162 .what is 162 plz tell me

4 Answers   L&T,


what is the mode of method of face bar measurement

0 Answers  


What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?

0 Answers   Gammon,


How many number of cement bags per running metre are required to cast pileof M-20 grade

1 Answers   Mantena,


How to calculate the Volume of PCC, Footing Base, Footing Column, Grouting, Base Plat and plinth beam

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)