what is the quantity of concrete required in 1 cubic meter volume without reinforcement
Answers were Sorted based on User's Feedback
Answer / iwuagwu chisom
Quantity of Concrete= Unit weight of concrete x Volume of concrete
Unit weight of concrete= 2400kg/m3
Volume of concrete= 1m3
Therefore, Quantity of Concrete= 2400kg/m3 x 1m3 = 2400kg
| Is This Answer Correct ? | 6 Yes | 0 No |
How to find out the quantity of steel FE415
16 Answers Bhel, L&T, TATA,
percentage of steel in one cubic meter of concrete
I am constructing a house having 20' X 19' hall. Do I need to go for a concealed beam. any alternative please? Thanks if a design is provided.
How many number of bars used in circular columns? Explain WHY?
What are the advantages of cad?
how you confirm the hard stratum for driven cat in situ pile work?
Doul Bar reinforcement and details of drawing.
0 Answers Atlanta Infrastructure,
why demand factor less then 1 ?
What"s mean by water bound macadam road(WBM)?
What is ideal location for cube casting, RMC vehical at Ground Floor and Slab casting at 40th Floor
Why the name is "partial safety factor" why not "safety factor"?
0 Answers Engineers India Limited,
explain fie benefits of using standard terminology in the measurement process
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)