In barbending schedule why is o.42*D is taken. Means why o.42 only???
Answer / arghya das
that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.
| Is This Answer Correct ? | 4 Yes | 0 No |
How calculate the Paint quantity for a wall?
where do Tie beams used in foundations?
HOW CAN DESIGN LENGTH,WIDTH AND HEIGHT THE FOUNDATION FOR THREE FLOOR BUILDING?
what is the ideal construction joint for slab?
what is anchorage length,lap length and (dont remember the last one)
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
how to know 28 day strength of concrete knowing 3 day or 7day strength of concrete???
what is temp. control concrete and what use of it ?
How Can Calculate Plastering Quantities For 260.04 square meter by using CM 1:4 with 25mm Thick ?
What would be the quantity of cement:Sand:Aggregate (1:2:4) requirement for slab casting measuring 1mtr x 1mtr x 0.10 mtr (4 inches)?
what is the significance of soundness test in Cement? and how is it done??
1 Answers Biltech Building Elements, Student,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)