How to calculate the condensate values of boiler?
Answer / prathab
cement consumption in plastering work
Plastering work
cemnt sand Total
Mortar 1:6 = 1 6 7
Length = 1 m
Height = 1 m
thickness = 12 mm
Toal area = 1 sqm
Total volume = 0.012 cum
Volume of mortar = 0.001714286 cum
The voids of sand we nead 20% extra material = 0.002057143 cum
Now add 20% eetra to cover uneven surface of brick work = 0.002468571 cum
One bag cement = 0.0347 cum
2 Quantity of cement required = 0.071140387 Bag
= 3.55701935 kg SI.NO DESCRIPTION UNIT QUANTITY
1 CEMENT Kg 3.56
3 Quantity of sand required = 0.014811429 cum
2 SAND Cum 0.0148
Is This Answer Correct ? | 0 Yes | 0 No |
How does iron ore turn into steel?
Why consumption of lubricating oil is more in two-stroke cycle petrol engine than four-stroke cycle petrol engine ?
what is the meaning of mumber ,which is given on bearing
What is the torque required at M6, M8, M10, M12, M14, M16, M18, M20, M22, M24 M.S&S.S Bolt or give me any chart for this?????????
What is the law of thermodynamics?
what is the function of a pt pump of a dg set
Name of any five measuring instruments?
What is the plant heat rate and what is the turbine heat rate?
which bearing use in lathe spindle
How to calculate motor bearing life - cycle (life time) (SKF bearing)
suppose if u selected ,when will u quit?
I'm a first year student of B.E Mechanical Engineering... How should i prepare myself for getting selected in campus interviews from now itself...? What books should i refer....?