Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how much time will take for G+22 building for completion?
activity wise like excavation,sub
structure,superstructure,finishing,handover?

Answers were Sorted based on User's Feedback



how much time will take for G+22 building for completion? activity wise like excavation,sub stru..

Answer / mohammed shahid

Well, there are many factors the completion duration depends
on and a duration for the project of G+22 cannot be derived
and said to be so-and-so months, as not everything stays
ideal and as planned.

1. For Excavation - Area of the building and the depth and
also the type of earth we're excavating. (Hard rock takes a
longer duration than the soil)

2. Sub-structure - As you've mentioned it is a G+22, i'm
assuming there is no basement but usually a G+22 has
2basements. Hence as per your question and details provided
we're omitting the basements but still the area of the
building plays a major role and also the structural (RCC)
vertical members and the types of foundations. If it is a
raft foundation, it takes lesser time with say A number of
manpower and if its isolated footings with a few combined
footings with the same A number of manpower then the
duration might triple.

3.Superstructure - Depends on the area, the vertical
members, the depth of the beams, structural projections,
number of lift shafts and staircases. One suggestion here is
the "SLAB CYCLE" can be derived and the same an be
multiplied by 22 for the entire structural (RCC) work of the
building.

4.Finishing - The same concept of "SLAB CYCLE" can be
derived and multiplied by 22 for the finishing duration of
the building.

5.Handover - This shall include attending to the snagging
list of activities and rectification works if any. the same
can be considered as approximately 60days.

Still if the Interviewer demands for a duration at the end
of the above explanation (presuming he will not), you can
give him an approximate figure of 24months maximum.

Is This Answer Correct ?    5 Yes 0 No

how much time will take for G+22 building for completion? activity wise like excavation,sub stru..

Answer / prashanth kumar

within 30 months from the start date

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

what is a pitot tube

5 Answers  


Plz tell me...column and wall section drawing.

1 Answers  


Can we apply curing compound on ceiling (slab Bottom)

0 Answers  


rasio for outer plaster thickness for wall

7 Answers   L&T,


Calculate the quantity of concrete for the following. 2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m length.

13 Answers  


how calucate cement sand ratio for plstering

0 Answers   DMRC,


I've beams dimensions of 9"x 18"x 45' please calculate the weight. Thanks

2 Answers   SRR Properties, Student, Treetop Solutions,


what is the weight of 8mm dia steel with 1 meter length. Is there any formula to calculate the weight for any given diameter

48 Answers   Benny Industries, D M Systems, L&T, MYC Infra, OL, PWD, Shell, SMB, SODI, Spyro Engineers, TNS, Welspun,


How much cement+aggregate+sand will be required for making K 150 ready mix for 1 CBM. Strength of Concrete is not mentioned only detail is K150, what i understand of K150 is the weight of cement and what does kg/m3 means.What will be the design for K300 concrete.

2 Answers  


What is the use of extruded feature in solidsworks?

0 Answers  


Please give a brief description of centre of gravity

1 Answers  


how to calculate the cutting length of steel? by which formula?

3 Answers   MS Khurana Engineering,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)