Answer / mohammed shahid
Well, there are many factors the completion duration depends
on and a duration for the project of G+22 cannot be derived
and said to be so-and-so months, as not everything stays
ideal and as planned.
1. For Excavation - Area of the building and the depth and
also the type of earth we're excavating. (Hard rock takes a
longer duration than the soil)
2. Sub-structure - As you've mentioned it is a G+22, i'm
assuming there is no basement but usually a G+22 has
2basements. Hence as per your question and details provided
we're omitting the basements but still the area of the
building plays a major role and also the structural (RCC)
vertical members and the types of foundations. If it is a
raft foundation, it takes lesser time with say A number of
manpower and if its isolated footings with a few combined
footings with the same A number of manpower then the
duration might triple.
3.Superstructure - Depends on the area, the vertical
members, the depth of the beams, structural projections,
number of lift shafts and staircases. One suggestion here is
the "SLAB CYCLE" can be derived and the same an be
multiplied by 22 for the entire structural (RCC) work of the
building.
4.Finishing - The same concept of "SLAB CYCLE" can be
derived and multiplied by 22 for the finishing duration of
the building.
5.Handover - This shall include attending to the snagging
list of activities and rectification works if any. the same
can be considered as approximately 60days.
Still if the Interviewer demands for a duration at the end
of the above explanation (presuming he will not), you can
give him an approximate figure of 24months maximum.
| Is This Answer Correct ? | 5 Yes | 0 No |
what is a pitot tube
Plz tell me...column and wall section drawing.
Can we apply curing compound on ceiling (slab Bottom)
rasio for outer plaster thickness for wall
Calculate the quantity of concrete for the following. 2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m length.
how calucate cement sand ratio for plstering
I've beams dimensions of 9"x 18"x 45' please calculate the weight. Thanks
2 Answers SRR Properties, Student, Treetop Solutions,
what is the weight of 8mm dia steel with 1 meter length. Is there any formula to calculate the weight for any given diameter
48 Answers Benny Industries, D M Systems, L&T, MYC Infra, OL, PWD, Shell, SMB, SODI, Spyro Engineers, TNS, Welspun,
How much cement+aggregate+sand will be required for making K 150 ready mix for 1 CBM. Strength of Concrete is not mentioned only detail is K150, what i understand of K150 is the weight of cement and what does kg/m3 means.What will be the design for K300 concrete.
What is the use of extruded feature in solidsworks?
Please give a brief description of centre of gravity
how to calculate the cutting length of steel? by which formula?
3 Answers MS Khurana Engineering,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)