tell me height of colum casting if slab height 3mtr beam thikness 500mm and slab thik 150mm ..

Answer / qs4freshers

Dear pankaj,

pl check the cross section details of the beam, if effective depth of beam is 500:
then add (500 + 150) effective depth of beam and slab thickness.
column height: 3.0 - (0.5+.15) = 2.35 M

if you find total dept of beam in cross section as 500
then :
column height: 3.0 - 0.50 = 2.50 M

Is This Answer Correct ?    16 Yes 1 No

tell me height of colum casting if slab height 3mtr beam thikness 500mm and slab thik 150mm ..

Answer / abhishek

2.350m

Is This Answer Correct ?    0 Yes 2 No

tell me height of colum casting if slab height 3mtr beam thikness 500mm and slab thik 150mm ..

Answer / vipin m

3ooo-500-150=2350..since at beam level reinforcement bars
has to be provided

Is This Answer Correct ?    1 Yes 9 No

Post New Answer

More Civil Engineering Interview Questions

What is bending movement formula define

1 Answers   L&T,


A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals

0 Answers  


Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method

0 Answers  


how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?

0 Answers   Bhoomi Engineers Builders,


B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS

0 Answers   TCE,






what are the criteria for choosing the span for the bridge (highway bridge)

4 Answers  


what is the minimum % of steel use in columns ?

7 Answers  


how we can calculate the quantity of sand & cement & also Aggregate so give me to this answer for a slab Length is : 25' /3.28 = 7.62 Mtr Width is : 30' /3.28 = 9.14 Mtr Depth is : 0.6"/3.28 = 0.15 2Mtr

3 Answers   Lotus,


How to find the concrete volume in sloped footing??? illustrate with example

1 Answers  


how to calculate no of rings in columns & weight of column rings & column ?

3 Answers   Al Tayeboon, HCC,


what is meant by MIS report

7 Answers   HCC, RiceLake,


why do we provide haunch for drains and culverts?

5 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)