Dear pankaj,
pl check the cross section details of the beam, if effective depth of beam is 500:
then add (500 + 150) effective depth of beam and slab thickness.
column height: 3.0 - (0.5+.15) = 2.35 M
if you find total dept of beam in cross section as 500
then :
column height: 3.0 - 0.50 = 2.50 M
Is This Answer Correct ? | 16 Yes | 1 No |
Answer / vipin m
3ooo-500-150=2350..since at beam level reinforcement bars
has to be provided
Is This Answer Correct ? | 1 Yes | 9 No |
What is bending movement formula define
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
0 Answers Bhoomi Engineers Builders,
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS
what are the criteria for choosing the span for the bridge (highway bridge)
what is the minimum % of steel use in columns ?
how we can calculate the quantity of sand & cement & also Aggregate so give me to this answer for a slab Length is : 25' /3.28 = 7.62 Mtr Width is : 30' /3.28 = 9.14 Mtr Depth is : 0.6"/3.28 = 0.15 2Mtr
How to find the concrete volume in sloped footing??? illustrate with example
how to calculate no of rings in columns & weight of column rings & column ?
what is meant by MIS report
why do we provide haunch for drains and culverts?