Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is the abbreviation & meaning of UI charges



what is the abbreviation & meaning of UI charges..

Answer / nagarajan

Un scheduled Interchange charges. This charges is being
collected by Regional Load Despatch Centre based on frequency
which is called ABT(Availability Based Tariff)Regulated by
CERC (Central Electricity Regulatory Commission)

Is This Answer Correct ?    8 Yes 3 No

Post New Answer

More Electrical Engineering Interview Questions

WHY IL=IPH IN STAR AND WHY IPH=IL/1.732 IN DELTA? WHAT IS REASON BEHIND IT?

0 Answers   Siemens,


what is the difference between the 94 lockout relay and 86 lock out relay. I have noticed that the 94 lockout relay is activated when the distance realy is activated and 86 is activated when the 87T differential is activated. but why can't the same lockouts be used for both the protection schemes

10 Answers   ABB,


how can check the resistance of battery contact?

0 Answers   Cipla,


battery spicgravity mesuserd?

1 Answers  


i want to know how to determine that a surge arrester work properly in 11kv system. and how to test a 12kv surge arrester

0 Answers  


why transformer not used to starter

1 Answers  


how to calculate the minimum permissible limts of insulation resistance of switchyard equipments

1 Answers   HVPNL,


why an ac solenoid valve attract the plunger eventhough we interchanges the terminal?will the ploes changes?

1 Answers  


In generally how many earthing required for power

4 Answers  


what is the acb tripping & closing voltage.

2 Answers  


what is brushless generator.How does work it..??

3 Answers   NTPC,


What happens to an electric motor if it has poor or no ventilation. Will it burn out? If it will, how long it will run before it burn out?

5 Answers   GMC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)