for columns reinforcement the lap length is not provided then
how to rebar the rods then how rebar should be lapped
Answers were Sorted based on User's Feedback
Answer / n.rajesh guttedar
1) In the columns portion chip the old concrete in a small
depth at least we get the tie beam rods.Then make L bend of a
columns rods and weld it.
2) In the columns portion drill a holes to insert the new rods
and pour the bonding chemical ( Bonding agent )
3) In the columns portion fix the MS plate with the required
holes for the holefasners insert.And make the columns in U
type shape and weld it.
Is This Answer Correct ? | 7 Yes | 1 No |
By welding the rod,and the welding should be in stagerred
type.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / suresh s
1st thing it should find that problem While Concrete Pouring Time immediately make The reinforcement at what length needed as per drawing.
2nd thing retrofitting method
3rd thing chip the column at lap height and tie the rod and weld it and pour the new concrete.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / sjtbehera
I think alternative step is welding and spiral binding
Is This Answer Correct ? | 0 Yes | 2 No |
Difference between overlap and development length of rod. Thanks.
Please let me know what is the simplest way of Calculating Mix Designs
WHICH BOOKS ARE AVAILABLE FOR CIVIL MPSC
If the first roof slab is not deshuttering in this time shall I start column raising work in second roof is it correct or not
2 Answers Al Fara, Unity Infraprojects,
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
what is the name of coarse sand which is used in making of concrete
explain yourself?
1 Answers Infosys, Omaxe, Siscom, TCE,
how many cubic ft. for 50 kg ( 1 bag ) cement?
What is factor of safety in the plastic method design?
what shape of coarse aggregates are ideal for concreting?
what is the permanent solution applied for restoration of leaning tower of pisa?
after temping in cbr mould keep how many hours mould in water