Answer / pragnesh
it's proportion for exampal 1:4, the parts of cement 1 and parts of sand 4.
now,
qty of cement per cu.meter from mortar= 1*1/(1+4)=0.2 cu.meter
qty of sand per cu.meter from mortar= 4*1/(1+4)= 0.8 cu.meter
Is This Answer Correct ? | 11 Yes | 20 No |
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation
what is the concrete mix design ratio of railway sleeper??????
what is concrete
Why we are not provide bar in the centre of the column and bar?
what would be the rqmnt. of cement and sand (1:6)for building brick wall and also 20mm thick plaster on the wall by same ratio?
what will be the grade of concrete for PCC having ratio 1:4:8?
what r remedies taken for foundation in black cotton soils..??
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)
how many stones require for rr masonery work 1cum.
what is the difference between sill beam,Tie beam and plinth beam?
why moment is create in fixed beam. And why moment is not create in simply support beam
quantity of cement required for M35 grade reinforced cement concrete