How to find the material quantity in a cement Sand mortar for
Stone masonry?
Answer / pragnesh
it's proportion for exampal 1:4, the parts of cement 1 and parts of sand 4.
now,
qty of cement per cu.meter from mortar= 1*1/(1+4)=0.2 cu.meter
qty of sand per cu.meter from mortar= 4*1/(1+4)= 0.8 cu.meter
| Is This Answer Correct ? | 11 Yes | 20 No |
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
why does the most of civil engg is not intersted to going for teaching field?
how much volume is one bag cement of 50kg
15 Answers Portland, RJB, UltraTech,
cement consumption per square feet in multi storeyed building
What is the use of offset command?
HOW MANY CUBES REQUIRED FOR 7 AND 28 DAYS TEST FOR ALL MIX GRADES.
4 Answers Ansals, HFCL, Jaypee, Pratibha Group,
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
how can change 12mmdia@150c/c bar spacing to 16mmdia
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
Explain the water bound macadam roag
How many types of Pile Foundation?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)