Answer / kuldeep singh sevariya
dry quantity of 1 cum wet concrete =1.54
730cft=20.67cum of wet quentity
so,dry quentity of 20.67cum=1.54*20.67=31.83cum
CEMENT=(31.83*1)/(1+1+2)=7.96cum
(Density of cement-1440kg/cum)
(7.96*1440)/50=229.176Bags
SAND=(31.83*1)/4=7.92CUM, SO, 1600*7.92=12672 KG
AGGREGATE=(31.83*2)/4=15.92 CUM
SO,1520*15.92=24198.4 KG
Is This Answer Correct ? | 14 Yes | 3 No |
Answer / mohammed aijaz hussain
Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.
Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.
Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags
Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.
Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.
Is This Answer Correct ? | 5 Yes | 2 No |
koi bta sakta ha ka steel ko calculate krna ka full mathod pls
What is passive earth pressure ?
What are the types of concrete
Explain soil analysis?
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
I'm constructing my house, now at lintel level. I need belt concrete with laft..length - 22ft, berth- 11ft, one side laft for 2ft, *22ft length. Kindly inform me centring cost only, without material cost.
how to consider the laping length of steel?
Explain creep?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
0 Answers Bhugan Infracon, UltraTech,
how clculate excavated or backfilling quantity by simpson's rule