Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is the procedure for erection of a transformer



what is the procedure for erection of a transformer..

Answer / debasis sahoo

During installation of Transformer on a Pole mounting structure, following checks should be made:
Ensure that the base channel of transformer is at height complying to IEC Standards:
a) Height of top of HV bushing from ground for pole mounted transformer should be 4.572 meters minimum (15 Ft)
b) Height of top of HV bushing from ground for plinth mounted transformer should be 2.75 meters minimum (8 Ft)

Ensure that base channel is horizontally leveled

Avoid jerky movement of the transformer while lifting it upwards during installation

During installation ensure that the HV bushings of the transformer are on the DO unit (or HG fuse unit) side of the structure

After installation of transformer, also check that other allied equipments such as AB switch, Horn Gap fuse units, DO Fuse sets, Lightening arrestor etc. are fitted at appropriate positions as per the applicable drawing issued by the utility.

Use PVC unarmoured cable (3 ½ core) of appropriate size and length for LV side. Ensure that the lugs are appropriately crimped at the ends.

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

what is the safety of VCB.

5 Answers   Nagarro, Roto Power, RotoPower,


If there are two transformer having rating of 2.5mva, 6.6kv/440v(satr-star),and the load is 600kw then what is better to maintain less losses in transformer having both transformer in parellel or only single transformer connected to load? Please give calculated answer

0 Answers   UltraTech,


how the synchronizing is obtained at bus couplers in grid substation? (because there we cannot change the frequency in one of transmission lines like in generator synchronization)

0 Answers  


A heater capacity is 3.0 KW on 415V . if supply voltage is 380Volt . what is heater capacity on 380volt . and how calculate and give formulas . Prakash veer singh Roto power Engg.

5 Answers  


What are the Formula of computing Back up Time of 500kVA UPS with 4 Battery Banks, each bank composed of 43 pcs of Batteries 12V150Ah. How to compute the Back up Time of UPS? We have also 3X500kVA UPS running in Parallel same composition as I write above.

0 Answers  


What are the material used for resistor?

0 Answers  


how u measure/calculate renge of capacitor,capacitor has no any rating tag.what is the theory of measure of capacitons.

0 Answers   Marriott,


What is the Temperature to be set in Thermostat provided in Marshalling box of the Transformer / Motor.

0 Answers   Kirloskar,


When we give supply to a transformer 11 kv and we get 415v from it, so when we give supply to same transformer 415v on ht side what we get? and When we gives supply to any transformer to L.T. side 415v or 220v What supply is on H.T. side?

2 Answers   Ashoka Electricals,


what is the different betweem earthing and neutral?

8 Answers  


why root three is used and how its comes in three phase power system?

1 Answers   IEEE,


In power transformer YnD0 Vector Group is possible or not? if possible, what will be the vector diagram and what are the conditions?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)