why we use casced loop
Answers were Sorted based on User's Feedback
Answer / ch amir islam
We use CASECAD loop to inhance the capability of the
process.normally we use this loop at BFW(boiler feed water)
tanks and at the BMS(burner managment system)to inhance the
burning ratio of fuel that become more relaiable for our
firing.because we are using here two controller(two
setpoints)these both controller makes process much more
flexible and accurate.
Is This Answer Correct ? | 4 Yes | 1 No |
Answer / ch amir islam
We use CASECAD loop to inhance the capability of the
process.normally we use this loop at BFW(boiler feed water)
tanks and at the BMS(burner managment system)to inhance the
burning ratio of fuel that become more relaiable for our
firing.because we are using here two controller(two
setpoints)these both controller makes process much more
flexible and accurate.
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / www.islamqa.com
Using cascade control enhance loop stability, as the
controller generatea corrective signal in case of any change
in process load - we don't need to wait till we got a
problem in the measured process variable (pressure,
temperature, ..)
Regards,
Ahmed Sabry
Control and Instrumentation Engineer
GPC - General Petroleum Company
CELL.: 00 2 0121367310
ahmedsabry.online@gmail.com
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sreekanth
If a PID Setpoint is derived from another PID then the loop
is called cascade loop.
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / vijay patel
cascade loop is used for the control of one perameter buy measure another perameter which is help to enhanse the stability of the loop.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / www.islamqa.com
Using cascade control enhance loop stability, as the
controller generatea corrective signal in case of any change
in process load - we don't need to wait till we got a
problem in the measured process variable (pressure,
temperature, ..)
Regards,
Ahmed Sabry
Control and Instrumentation Engineer
GPC - General Petroleum Company
CELL.: 00 2 0121367310
ahmedsabry.online@gmail.com
Is This Answer Correct ? | 0 Yes | 1 No |
Is it possible to drill additional gland hole in EExd or EExe JBs? What are the points to take care?
how to derive kg/cm2 to mmwc? complete derivation.
What is the Main principle and formula for the steam flow compensation?
If an Instrument has 550 ohm internal resistance and the cable used for that instrument is 0.5 ohm per meter resistance. If the voltage is 12volt.How much length cable can be used? Please tell me its Calculation formula.
WHICH IS BEST INSTRUMENTATION OR ELECTRICAL ENGG?
How a conductivity sensor & analyzer work at boiler, whats the principle & science is beyond this,How conductivity sensor sence & convert signal & move toward analyzer & analyzer show reading in percent? also what is temperature compensate option in conductivity analyzer
What is standard procedure of manual mapping in Radar type level transmitter?
Sir,I am going to sit for IOCL written test exam. recently.Can anyone tell me the name of 'Objective type Question Book on Instrumentation Engineering ' which will help me. Pl. mail to bidyut_71@rediffmail.com / bidyut.saha2008@indiatimes.com / bidyut.saha09@yahoo.in
why we use 24 vdc in instruments mostly?
why metallic housing is provided of solenoid valve.
Explain operation of Haskel pump.
please send me hpcl placement papers