How Much span required for 1 sqm of shuttering(Beam & Slab)
Answers were Sorted based on User's Feedback
Answer / sumeet rathod
1.for 1 sq/m slab reqired = 2span @ .600c/c
2.for beam support vertical iron props are required always, 1st prop kept from column at a distance of .230 and than .600 c/c
Is This Answer Correct ? | 8 Yes | 5 No |
What is the Maximum %age of Steel in columns and beams ?
this is jagdesh from vizag, IM GOING 2 ATTEND BHEL interview on 14th dec. im a civil engg. graduate. plzz let me know the pattern & few questions of the interview if possible. plz reply at jd_marc@yahoo.com
curing of concrete why 7day's,14day's 21day's 28days
what is the grade of 1:2:1 concrete mix
Pl answer. when we deduct 2d for cutting length of 90deg bend, whats the method of booking measurements as per IS code? whether cutting Length to be booked or something else?
How do piles bear loads
What is the meaning of Fe415 ?
6 Answers Arul Constructions, L&T, SSM,
what is curing?
If in school there are 1800 students and 80 staff how much water can be used by them per day?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
What is the exact definition of national highway. What is the difference between national highway n any other road?
how to carry out rate analysis for RCC work in column using M20 ?
1 Answers Mazna Building Contracting,