Answer / prabhat kumar shahi

frist in the crush sand 100% passing threw 4.75 m.m. sieves
& retain 85%in 150 microns & this manufacture from crush by
rock.and grit powder passing threw 150 microns sieve 50%
generally now 50% to 60% use in mix-design. nest year used
100% VSI crush sand MIX-DESIGN we are produce.

Is This Answer Correct ?    7 Yes 4 No

what is the maximum percentage of crush sand in mix design.also what is the difference betweeen gr..

Answer / sanjay u ojha

crush sand are made by rock in majority. however near the
source of river it is produce by sand pebbles. crush sand by
pebble are almost round in shape however of rock is angular.
sand using pebble can be used 100% for concrete and of rock
shall be @50 yo 70%. However due to ban in maharashtra by
environment dept, now a days 100% crush sand are used for
mix design.

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how many AAC blocks of size 600*200*225 mm are required for 1 cu.m of area

1 Answers  


does a b.tech civil engineer fresher supposed to know how to design rcc structure?

0 Answers  


Please i want to know how to find column main bar cat of length

0 Answers  


why are you joining in this (applied post) job and your aim for this job

0 Answers   APPSC,


On concrete surface 1sq.ft area hacking no's of hack?

7 Answers  






what bending moment?

3 Answers  


how sir calculate the slab steel and sir i want to know that how i calculate shutter works payments in cum and the rate is 120 per cum

1 Answers  


how to calculate unit weight cement ,water ,steel

2 Answers   L&T, SVS,


What is the density of Cement, Fly ash,20 mm aggregate, 10 mm aggregate and stone dust?

14 Answers   Amrapali, Egis, Himuda, Indramas, L&T,


what is the difference between built-up area & carpet area? how to calculate this areas?as there are any formula to calculate these areas?

6 Answers   Dimension Data,


1 cum brick work CM1:6 how many bricks sand cement required brick size 8"4"3"

3 Answers  


what,s the clear cover of beam,slab,column,lintel and foundation?

36 Answers   Max Myanmar, Spar Geo Infra, Yashwant Construction‎,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)