tell me quantitys of matal, sand and cement in 1:4:8 and
1:2:4
Answers were Sorted based on User's Feedback
Answer / tejaswi
for 1 unit of cement , 4 units of sand and 8 units of
matal are added in 1:4:8 mix.
And for 1 unit of cement, 2 units of sand and 4 units of
matal are added in 1:2:4 mix.
Is This Answer Correct ? | 166 Yes | 39 No |
Answer / ramesh
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
40mm metal :0.92 cum
sand :0.46
cement :0.115 cum or 3.312 bags
Is This Answer Correct ? | 127 Yes | 20 No |
If you are considering 1:4:8; per each cubic meter you have
to arrive the quantities as under.
If 1+4+8= 1cum (dry mix); then
cement quantity will be 1/13 = 0.077 cum;(2.2 Bags of 50kg)
Sand Quantity will be 4/13= 0.31 cum and
the Quantity of Coarse aggregate shall be 8/13=0.62 cum.
But, the volume of dry concrete will be 1.5 times
(approx)the volume of wet concrete. So, if you want to
prepare a cum of wet concrete, multiply the above values by 1.5.
Is This Answer Correct ? | 90 Yes | 21 No |
Answer / mask
* In 1:4:8
Cement - 1.25 Cft
Sand - 5 Cft
Matal - 10 Cft
*In 1:2:4
Cement - 1.25 Cft
Sand - 2.5 Cft
Matal - 5 Cft
Is This Answer Correct ? | 45 Yes | 10 No |
Answer / navneet
the mix contains 1 part of cement, 2 parts of fine aggregate
and 4 parts of coarse aggregate
Is This Answer Correct ? | 23 Yes | 7 No |
Answer / narendra pawar
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
metal :0.616 cum
sand :0.308
cement :0.077 cum
0.077 + 0.308 + 0.616 = 1.001 cum
Is This Answer Correct ? | 26 Yes | 12 No |
Answer / vishal kumar chy
1:2:4 It means 1 unit of cement, 2 units of sand , 4 units of aggregates
Is This Answer Correct ? | 13 Yes | 2 No |
Answer / kailash
1:2:4 & 1:4:8 its not a standard design. design depends
upon the which aggregate available at site and there
density.
Is This Answer Correct ? | 10 Yes | 10 No |
Answer / suraj
in 1:2:4 mixture 1 part is cement 2 part is coarse sand and
4 part is fine sand matal is nothing
Is This Answer Correct ? | 16 Yes | 27 No |
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
how i can tak Quantity of mortar in block work
What is the meaning of a blue land surveyors flag?
How many no of bricks form 1 cum? How many no of solid blocks form 1 cum?
How to evaluate the elastic modulus of soil from the plate load test result? for example ..one of test results are here Max. settement =4.56mm(at 900kPa) Residual settlement = 4.02mm Maximum pressure on soil 900kpa Soil bearing capacity 300kpa Plate diameter=300mm Thickness =25mm Soil description =Grey, clayey silty SAND with gravels and rock fragments
How to design staircase.plz tell me formula for the design the staircase.
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
How to calculate numbers of carpenter, fitter, mason, unskilled worker on the basis of built up area or floor plat area of building?
What is differences between torsion and buckling?
what is the 0 value in quantity surveying
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1 M3,10M2,1 TON RESPECTIVELY