Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How much does it cost for a R.C.C roof slab of size (25 X
20) given in feets using 1:2:4 concrete mix of M20?

Answers were Sorted based on User's Feedback



How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / bong/mustafa

r.c.c roof slab given = 25*20,

25ft=m/3,28ft=7,62*6.097= 46.46 m2

vol = 9.28 = 10 bags =
= 20 cub =
= 40 cub =

Is This Answer Correct ?    68 Yes 27 No

How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / soumya

rate of M20 concrete per cum= Rs.2900
labour charge=250 rs
shuttering cost=300
total =2900+250+300=3450/cum
here area given as =25*0.3048*20*0.3048=46 sqm
assume roof thickness as 10 cm
there for Qty =46*0.10=4.6 cum
cost of rcc roof =4.6*3450=15870

Is This Answer Correct ?    55 Yes 29 No

How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / dharmaraja mk

Concrete slab area = 25' x 20'
= (25x.3048)x (20x.3048)
= 7.62 x 6.096
= 46.451 Sqm
The IS CODE is recommended the minimum roof slab thickness is 125mm.
= 46.451 x .125
= 5.806 CUM
The RMC rate approximate 3000/cum.
Labour Mason-3no, mc-4no
= (3x500)+(4x350)
= 2900
Concrete coste = (5.806x3000) + 2900
RS = 20319
If it is not calculate for Shuttering cost.

Is This Answer Correct ?    37 Yes 15 No

How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / muzaffar hussain

roof concrete size width 40 feet length 53 feet(plz send me estimate stone quantity & size sand cement and labor charges

Is This Answer Correct ?    6 Yes 0 No

How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / lalit kumar sharma

i want to do a rcc slab 19*19 how much total all cost, iron, sand, dust rodi, cement

Is This Answer Correct ?    1 Yes 0 No

How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / kage

All given answers are thumb rules . No body has calculated from basics. This is the reason they are converting the sizes in to metric. because the thumb rules available with them are in metric sizes.

Is This Answer Correct ?    1 Yes 0 No

How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete m..

Answer / gokul

I want build water tank in rcc, size L-20ft x B-17ft x H-12ft. Wall thickness 0.75ft. Please give construction price.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How to calculate strirubs hook length? one of my friend said unit of steel*dia of steel*no of bend=hook length is correct r wronge

3 Answers  


name three materials used in drainage work

7 Answers  


Lap length may different for FE 415 and FE 500 Steel, If different what is the different, In which code is mentioned

3 Answers   Bestech,


quick sand is a type of sand flow condition occuring in cohesive soil flow condition occuring in cohessionless soil all above

1 Answers  


what is meant by workebility of concrete?i have studied about it much but i can't clear about it.so plz give me a detail explanation in simple english or urdu ?

1 Answers  


Specific gravity of cement?

0 Answers  


If your drg told used 600 dia hume pipe for culvert but due to market problem available 300 dia hume pipe,den how much humepipe you provide(300 dia) instead of 600 dia?

1 Answers  


How to calculate the quantity of water in cement mortar eg. CM 1:3?

2 Answers   FuRyu,


how much steel required for 1 sq.m area?

24 Answers   AA Architects, L&T,


what is the average steel consumption in multy storey building as a residential and commercial?

6 Answers  


what is the compresive strength of m20 concrete at 7 day

15 Answers  


M20 Grade ratio? M30 Grade ratio? M40 Grade ratio ?

30 Answers   AB Group, Aparna Enterprises, CECL, Engineers India, intex, Jain Group, Keystone, L&T, Multi Engineering, National, Shrinath Buildcon,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)