Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how you calculate the qty. of cement ,sand,aggregate from
proportion 1:2:4 M15

Answers were Sorted based on User's Feedback



how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15..

Answer / bala

Ratio 1:2:4 as u know
1-Volume of cement
2-volume of fine aggregate
4-volume of coarse aggregate

1 bag of cement = 1 1/4 Cft so the gauge box measures the
same
so sand twice the gauge box (2*one onefourth Cft)
and coarse aggregate four times the gauge box(4*one
onefourth Cft)

Is This Answer Correct ?    20 Yes 12 No

how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15..

Answer / james

For ratio 1:2:4
1 - one head pan of cement
2 - two head pans of fine aggregate
4 - four head pans of coarse aggregate

Is This Answer Correct ?    7 Yes 2 No

how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15..

Answer / sindhumani

To find the individual ratio of materials we have to use one
formula,
Sand = 0.46% of cement
Aggre= 0.92% of cement

For ratio 1:2:4
to find cement qty: (0.46%/2)*1440kg= 331Kg
For ratio 1:3:6
to find cement qty: (0.46%/3)*1440kg= 221Kg

Is This Answer Correct ?    3 Yes 2 No

how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15..

Answer / vinod kumar,sriharikota

quantity of cement = 1/7=0.1428 cu.m

quantity of fine aggregate = 2/7 =0.2857 cu.m

quantity of coarse aggregate = 4/7 =0.5714 cu.m

total = 0.1428+0.2857+0.5714 = 1.000 cu.m

Is This Answer Correct ?    3 Yes 3 No

how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15..

Answer / viplav

while using the proportion

Is This Answer Correct ?    5 Yes 12 No

Post New Answer

More Civil Engineering Interview Questions

indian standard split spoon sampler

0 Answers   Amrapali,


does the compressive strength of brick be more then 3.5 n/mm2 or 5 n/mm2?

3 Answers   L&T, Modi Builders,


Process of pcc in wateredug

0 Answers  


estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?

0 Answers  


what is mixed design, define it? what is way beecher?

3 Answers   Gammon, L&T,


Volume of 25kg putty bag & 40 kg putty bag volume??

0 Answers   NCCL,


Can i have pumpable mix design for M10 concrete without fly ash with OPC 43G cement?

1 Answers  


what if tie beams coming from x axis do not meet tie beam coming from y axis? Is it safe if they dont meet?

2 Answers  


significance of specific surface area of particles?

0 Answers   Gammon,


what is the heart of civil engineering

12 Answers   Ramky,


What is the meaning of "TOR" ??

2 Answers  


difference b/w stress and strength

3 Answers   BMS,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)